We’ll deliver on Ogbemudia Stadium Complex’s gymnasium by March 13, contractor says

Gymnasium
By Monday Ajogun
Benin, Feb. 25, 2020 (NAN) Peculiar Ultimate Consult, the contractors handling the reconstruction and upgrading of the Samuel Ogbemudia Stadium Complex in Benin, on Tuesday assured that the gymnasium building would be ready before March 13.

Olanrewaju Adeleke, the company’s Chief Executive Officer (CEO), gave the assurance shortly after he conducted journalists round the gymnasium building.

“We are going to keep with the timeline, and by March 13 we should be done. The construction work at the gymnasium has been going at a very fast pace.

“This is the only major construction work remaining in the Samuel Ogbemudia Stadium, and by March 13, we should have finished.’’

Speaking on the Games Village located at the University of Benin, the company CEO said they have four weeks to work on the facility.

“The students vacated the hostel on Thursday, being Feb. 20, and we have four weeks to work on the Game Village since the athletes will be coming in by March 20.

“But by the programme of work, we have three weeks, counting from Feb. 20, to get things done.

“However, a visit to the university now will show that our people have been working massively to meet that target,’’ he said.

Adeleke assured that the venue would be ready one week to the event.(NAN)